Thermal insulation of the building envelope of the Daytime Rehabilitation Centre and Day-Care Centre for children under three years of age in Most

Home / References / Construction division / Thermal insulation of the building envelope of the Daytime Rehabilitation Centre and Day-Care Centre for children under three years of age in Most
#
#
#
#
#
#
#
#
Investor:
Statutory city of Most
Implementation deadline:
July 2022 – September 2022

Our construction division carried out all work during normal site operation.

The following works were carried out:

  • demolition work
  • interior reconstruction
  • ground work
  • roads
  • thermal insulation
  • sanitary equipment installations
  • installation of lightning conductor systems

The result was a reduction in the energy consumption of the building.