32 DN 800 pontoons and 16 pcs of DN 560 conveyor pipes made of PE80 material were manufactured.
Out of these components, 16 pieces of floating pipeline were assembled, which were gradually transported to the water surface and connected into a total pipeline route of 200 m. This pipeline is used to transport fly ash on the water surface of Lake Venus.